FEATURED PROJECT - SANTA CLARITA COMMUNITY COLLEGE LIBRARY ADDITION
Project Description: 52,000 sf library addition.
Project Details: Complete installation of mechanical systems using Bim Revit Models -including underground and above ground hydronic distribution, Auto logic DDC controls system, Fabrication and installation of rectangular and round ductwork using ,vav installation and hot water reheat systems,exhaust and air distribution installation.
- Project Time: 8 Months
- Equipment Count/Schedule: 2 Alliance air Handlers ,2 B&G pumps ,33 vavs with water reheat, auto logic DDC controls sytem,Frp ,PVC, Steel and copper piping systems.Vibra coustics sound traps.